Cost by Project
Cost by Category
Cost Over Time
Top 20 Cost Events
| Project | Cost Code | Source | Description | Total |
|---|---|---|---|---|
| Office Tower A | 03-2100 | Subcontractor | Foundation work | $45,000 |
| Highway Bridge | 31-2300 | Equipment | Heavy excavation | $38,000 |
| Hospital Wing | 05-1200 | Materials | Structural steel delivery | $32,000 |
| Office Tower A | 26-0500 | Labor | Electrical rough-in | $28,500 |
| School Renovation | 09-2100 | Subcontractor | Drywall installation | $25,000 |
| Highway Bridge | 03-2100 | Materials | Concrete pour | $22,000 |
| Hospital Wing | 22-1100 | Subcontractor | Plumbing rough-in | $19,500 |
| Retail Complex | 07-2100 | Materials | Roofing materials | $18,000 |
| Office Tower A | 08-1100 | Materials | Curtain wall | $16,500 |
| School Renovation | 26-0500 | Labor | Electrical finish | $15,000 |